Bell’s plans for its Canadian AI Fabric network include a 500 MW data centre cluster in British Columbia and a campus outside Regina that could eventually reach 1.2 GW. Across the network, Bell plans to use common engineering standards for power and cooling and to test those systems together before each facility enters service.
Bell initially planned 300 MW of capacity for its Saskatchewan campus in the Rural Municipality of Sherwood. An agreement with the province allows Bell to pursue up to 900 MW more in phases, subject to customer commitments, commercial agreements and approvals.
Two open director roles in Calgary offer a closer look at how Bell intends to carry out those plans across its seven planned high-density data centres.
The director of engineering and procurement will oversee designs for grid connections, backup generation, uninterruptible power supplies and liquid cooling. Reporting to Bell’s vice-president of capital programs, the director will also select suppliers and time equipment orders around construction schedules, particularly for components with long lead times.
The director of data centre commissioning will set the tests each site must pass before operators take it over. Testing starts at the equipment factory and continues after installation, when crews check that power, cooling and backup systems work together.